What is stability certificate and What are the requirements for Stability certificate based on Indian Health and Safety Legislation?
Answer:
Approval,
licensing and registration of factories Sec 6 “Approval of plans” contains requirements of stability certificate.
State
|
Frequency, Rule and Form
|
Tamilnadu
|
Every 3 years
|
Andhra Pradesh
|
One time only
|
Kerala
|
Every 5 years
|
Uttar Pradesh
|
One Time, Rule 03, Form 2.
|
Madhya Pradesh
|
One Time, Rule 3A, Rule 123 , Form 2
|
Maharashtra
|
Every Five Years, Rule 3A, Form 1A
|
Gujarat
|
Every Five Years, Rule 3C, Form 1A
|
Himachal Pradesh
|
One Time, Rule 3A, Form 2
|
Punjab
|
One Time, Rule 4, Form 1F
|
Stability certificate signed by a competent person with below statement:
I (Competent Person) certify that I have inspected the building/buildings, the plans of which have been approved by the Chief inspector of Factories.I am of the opinion that the
building/buildings which has/have been constructed/reconstructed/extended/taken into use is/are in accordance with the plans approved by the Chief Inspector in his letter mentioned above.
Building/ Buildings are structurally sound and that its/their stability will not be endangered by its/their use as factory/part of a factory for the manufacture of .......... for which the machinery, plant, etc. installed are intended.
Who is Competent Person?
(4)
The person signing the stability certificate shall possess one or other of the
following qualifications :
(a) Corporate membership of any of the
following institutions :
(i) The
Institute of Civil Engineers.
(ii) The Institute of Structural
Engineers.
(iii) The Royal Institute of British
Architects.
(iv) The Institute of Engineers (India)
together with a degree of a recognized Civil Engineering College in India;
provided that he has also been for three years in bona fide practice on his own accounts as Chief
Assistant of a recognized firm of Civil Engineers, or
(b) Such other qualifications as the
Chief Inspector of Factories may approve.
So, Chief inspector of factory ask occupier to start manufacturing after stability certificate by a competent person.No manufacturing process shall be carried out in any premises of a factory unless a fresh certificate of stability is obtained from a competent person
Different states requirement of stability certificate, its frequency, rules and Form.
Note:
1- Stability Certificate is also required when after extension, alteration, repairs or addition
of any work of engineering construction or replacement or addition of machinery, plant, etc.,
and sent to the Chief Inspector.
2- No person except in the case of building occupied by any Government shall be authorized to sign a Certificate of Stability, who is in the employment of the owner or builder of the building in respect of which the certificate is given.
Stability Certificate Format:
1. Name of the factory .....................................
2. Village, town and district in which the factory is situated ......................................
3. Full postal address of the factory ......................................
4. Name of the occupier of the factory ......................................
5. Nature of manufacturing process to be carried on in the factory .....................................
6. Number of floors on which workers will be employed ......................................
I certify that I have inspected the building/buildings, the plans of which have been approved by the Chief Inspector in his letter No.... ............ dated ......... and examined the various parts including the foundations with special reference to the machine, plant etc., that have been installed. I am of the opinion that the building/buildings which has/have been constructed/reconstructed/extended/taken into use is/are in
accordance with the plans approved by the Chief Inspector in his letter mentioned above, that it is/they are structurally sound and that its/their stability will not be endangered by its/their use as factory/part of a factory for the manufacture of .......... for which the machinery, plant, etc. installed are intended.
Signature ..............................
Qualifications .........................
Address ...............................
Date .................................
Nice post. I read many things on different blogs everyday.
ReplyDeleteIt will always be stimulating to read content from other writers and practice a little something from their store. I'd like to share my blog link on your blog and Naturally I'll give you a link on your web blog. Thanks for sharing.
Health and Hospitality Management